Skip to main content

Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

COSMOS i10 Reassignment Discussion

Agenda

  • Which resources have bandwidth to take on additional i10 work?
  • Prioritization of i10 enhancements requiring additional resources:
    • 220949 (Hubert) - MDRs need to accept vanilla web service requests
    • 220952 (Hubert) - Broker to manage MDRs that do not support WSA and WSRF
    • Work that need to be done as a result of 220949 and 220952:
      • bug 224587: Port/test logging data manager example to axis2 (0.5 day)
      • bug 224589: Port/test statistical data manager example to axis2 (0.5 day)
      • bug 224592: Port/test example MDR example to axis2 (0.5 day)
      • bug 224593: Port/test sml repostiroy MDR example to axis2 (0.5 day)
      • bug 224595: Port/test example registration service to axis2 (1 day)
      • bug 224596: Changes in UI as a result of broker API changes
      • bug 224600: Changes in UI as a result of SOAP message changes
      • bug 224601: Demo: config program (0.5 day)
      • bug 224608: Demo: Command line client for administrering COMSOS components (1 day)
      • bug 224610: Build changes (2 days)
      • bug 224612: test and document end2end scenario for i10 (1 day)
    • 220955?? (Hubert) - Deregister Data Managers from the Broker - Hubert can contain it as part of 220952.
    • COSMOS 1.0 Documentation Table of Contents Documentation enhancements - Are there any sections that require additional resources to complete?
    • Proposal for Data Visualization bugs & enhancements to be potentially added to i10
  • Of the available resources, who should we assign to these enhancements based on priority and skills match?


Summary of 3/28 Discussion

Attendees: Tania, Martin, Rich, Paul, Ali, Hubert, JT, David, Ruth, Domenica, Jack, Sheldon


Available Resources:

  • Sheldon, JT and Martin potentially have bandwidth to pick up additional i10 work
  • Len is fully booked
  • Bill could be made available if we deferred the Aperi work


The additional Data Collection work cannot be started until Hubert completes his work at the end of next week (4/4). Therefore, the DV team can use next week to work on DV items and then roll over to DC the following week.


Plan for Week of 3/31:

  • 222982 - Sheldon
  • 221901 - JT
  • Data Visualization Bug fixes - Sheldon, JT, Martin

By 4/4, we can assess the remaining DV bugs and determine which ones should be deferred to i11.


Plan for Week of 4/7:

  • JT will help with DC work
  • Sheldon and Martin will continue work on DV bugs unless more help is needed on DC

By 4/9, we can assess how the porting is going and determine whether or not we need more of the DV team to help.


Documentation:

  • No one expressed concerns with meeting their documentation input dates.

Back to the top