Attendees
- John Graham
Regrets
Agenda
- Announcement: Roy, Eden (Zend), Wolfgang (SAP), Lin (Sybase) are now Enablement committers
- Review of database support levels
- DTP 1.6M5 is due to Ganymede on 2/11 (M)
- Following the Sign-off Policy, I suggest a sign-off date of 2/8 (F) and candidate build date of 2/6 (W).
- This means 12 working days (including today) until candidate build.
- About 26 bugs open with tm of 1.6M5, which would mean a closure rate of about 2 per day, not counting incoming bugs.
- Concerned about risk/changes associated with 208455 (removal of SDO dependencies).
- Review of bugs with no target milestone set.
- Open discussion