Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
DTP PMC and Project Lead Meeting Minutes: January 21, 2008
Revision as of 13:24, 21 January 2008 by Unnamed Poltroon (Talk) (New page: ← Back to DTP PMC and Project Lead Meeting page ==Attendees== *John Graham ==Regrets== ==Agenda== *Announcement: Roy, Eden (Zend), Wolfgang (SAP)...)
← Back to DTP PMC and Project Lead Meeting page
Contents
Attendees
- John Graham
Regrets
Agenda
- Announcement: Roy, Eden (Zend), Wolfgang (SAP), Lin (Sybase) are now Enablement committers
- Review of database support levels
- DTP 1.6M5 is due to Ganymede on 2/11 (M)
- Following the Sign-off Policy, I suggest a sign-off date of 2/8 (F) and candidate build date of 2/6 (W)
- This means 12 working days (including today) until candidate build
- About 26 bugs open with tm of 1.6M5, which would mean a closure rate of about 2 per day, not counting incomming bugs
- Review of bugs with no target milestone set.
- Open discussion