Skip to main content

Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "DTP PMC and Project Lead Meeting Minutes: January 21, 2008"

(New page: ← Back to DTP PMC and Project Lead Meeting page ==Attendees== *John Graham ==Regrets== ==Agenda== *Announcement: Roy, Eden (Zend), Wolfgang (SAP)...)
 
Line 9: Line 9:
 
**Following the [[DTP_Ganymede_Milestone_Sign-off_Policy | Sign-off Policy]], I suggest a sign-off date of 2/8 (F) and candidate build date of 2/6 (W)
 
**Following the [[DTP_Ganymede_Milestone_Sign-off_Policy | Sign-off Policy]], I suggest a sign-off date of 2/8 (F) and candidate build date of 2/6 (W)
 
**This means 12 working days (including today) until candidate build
 
**This means 12 working days (including today) until candidate build
**About 26 bugs open with tm of 1.6M5, which would mean a closure rate of about 2 per day, not counting incomming bugs
+
**About 26 bugs open with tm of 1.6M5, which would mean a closure rate of about 2 per day, not counting incoming bugs
 
*Review of [https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=allwordssubstr&short_desc=&classification=DataTools&product=Data+Tools&target_milestone=---&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&field0-0-0=noop&type0-0-0=noop&value0-0-0= bugs with no target milestone set].
 
*Review of [https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=allwordssubstr&short_desc=&classification=DataTools&product=Data+Tools&target_milestone=---&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&field0-0-0=noop&type0-0-0=noop&value0-0-0= bugs with no target milestone set].
 
*Open discussion
 
*Open discussion

Revision as of 13:25, 21 January 2008

Back to DTP PMC and Project Lead Meeting page

Attendees

  • John Graham

Regrets

Agenda

  • Announcement: Roy, Eden (Zend), Wolfgang (SAP), Lin (Sybase) are now Enablement committers
  • Review of database support levels
  • DTP 1.6M5 is due to Ganymede on 2/11 (M)
    • Following the Sign-off Policy, I suggest a sign-off date of 2/8 (F) and candidate build date of 2/6 (W)
    • This means 12 working days (including today) until candidate build
    • About 26 bugs open with tm of 1.6M5, which would mean a closure rate of about 2 per day, not counting incoming bugs
  • Review of bugs with no target milestone set.
  • Open discussion

Minutes